Smart Metering Program • MAP Onboarding

Meter Asset Provider Engagement Process

Comprehensive onboarding roadmap, statutory checklists, and 4-phase engagement framework for prospective Meter Asset Providers partnering with Kaduna Electric.

12-Stage RoadmapNERC Approved MAP RegulationSmart AMR / AMI Standard30% Minimum Local Content

Important Notice on Statutory Deadlines:

If initial Supply Chain Management (SCM) criteria are incomplete, the applicant will receive official notification requiring all outstanding documents to be resolved within Ten (10) business days to preserve quota allocation.

PHASE 01

Application & Due Diligence

Initial EOI, documentation packs & technical vetting

3 Milestones
01Applicant Action

Expression of Interest (EOI)

Prospective MAP officially transmits a formal EOI letter addressed to the MD/CEO of Kaduna Electric.

Stage Complete
02MAP Office

EOI Response & Application Pack

The MAP Project Office issues a formal response letter attaching the comprehensive MAP Application Form.

Stage Complete
03SCM Evaluation

RFI & Procurement Checklist

Supply Chain Management (SCM) issues a detailed RFI checklist verifying statutory, technical, and financial criteria.

Stage Complete
PHASE 02

Allocation & NERC Permitting

Provisional quotas & regulatory operating permit

3 Milestones
04Quota Allocation

Provisional Letter of Engagement

SCM issues a signed Provisional Engagement Letter stating assigned feeder zones and single/3-phase quantities.

Stage Complete
05Regulator Clearance

NERC Permit Application

The Applicant submits the Engagement Letter to NERC as a prerequisite for their official MAP Operating Permit.

Stage Complete
06Vendor Onboarding

Complete SCM Registration

Applicant deposits certified copies of the approved NERC Permit and Engagement Letter with SCM to finalize registration.

Stage Complete
PHASE 03

MSA Contract Execution

Rollout schedules, legal sign-off & data keys

3 Milestones
07Workplan Submission

Notice of Registration & Schedules

SCM requests detailed area office rollout matrices, installation schedules, and certified expert CVs.

Stage Complete
08MD/CEO Sign-Off

Executive Contract Approval

SCM submits the complete appraisal dossier and contract approval request to the MD/CEO and Chief Legal Adviser.

Stage Complete
09Final Agreement

MSA Legal Execution

The Legal Directorate executes the formal Metering Service Agreement (MSA), issuing the Final Engagement Letter.

Stage Complete
PHASE 04

Field Rollout & Joint SLA

Customer deployment, telemetry & continuous monitoring

3 Milestones
10Operational Launch

Joint Kick-Off & Data Integration

The MAP Office convenes a kick-off meeting with Executive Management, releasing customer data and API keys.

Stage Complete
11Mass Rollout

Field Deployment & Installations

The Registered MAP mobilizes certified technicians to commence smart meter installations and token initialization.

Stage Complete
12SLA Auditing

Joint Performance Reviews

A Joint Monitoring Committee transmits weekly deployment reports to the CEO and conducts monthly SLA audits.

Stage Complete
MAP Partnership Gateway

Ready to Partner with Kaduna Electric?

Submit your formal Expression of Interest to the Supply Chain Management directorate or view standard MAP meter pricing schedules.